JDE Reference
31Shop Floor Management
Supply chainWork order execution, parts lists, and routing instructions for the manufacturing floor
3 tables8 programs
Verified September 2026
In the business-problem map Manufacturing & Production
Tables
Transactional · 3
- F3102One row per cost bucket on a work order — keyed by order, item, cost component, parent/child flag, and work center — holding standard, current, planned, actual, completed, and scrapped units and amounts used for manufacturing variance analysis.transaction
- F3111Work order parts list — one row per component required by a work order, with required vs. issued quantities, scrap, commitments, and the operation each part feedstransaction
- F3112Work order routing — one row per operation on a work order, carrying the work center, standard vs. actual machine/labor/setup hours, and quantities completed or scrapped at each steptransaction
Programs
- P3111Work Order Parts List — the screen for reviewing and revising the components attached to a specific work order, including substitutions and commitment changes.Interactive
- P31113Work Order Inventory Issues — the screen that issues component material to a work order, relieving on-hand inventory and writing IM transactions to the item ledger.Interactive
- P31114Work Order Completions — the screen that records finished goods coming off a work order, moving completed quantity into on-hand inventory and updating order status.Interactive
- P3112Work Order Routing — the screen for revising a work order's routing steps: work centers, operation sequences, run hours, and outside operations.Interactive
- P31123Super Backflush — the screen that reports completions at pay points and backflushes material issues and labor for all prior operations in one transaction.Interactive
- R31410Order Processing — the batch job that attaches the parts list and routing to work orders, commits inventory, and prints shop floor paperwork in one pass.Batch UBE
- R31802AManufacturing Accounting Journal Entries — the batch job that turns unaccounted work-in-process and completion units into G/L journal entries and updates production cost records.Batch UBE
- R31804Variance Journal Entries — the batch job that books manufacturing variances (engineering, planned, actual, other) to the G/L when work orders close.Batch UBE